1. News Center
  2. Media Center

The First Shipment for 26MW Power Plant Pass Through the Factory Testing

Date:2012-12-18     Views:2012

From December 10th to 14th, The first shipment for 26MW Middle East Power Plant project pass through the factory testing. The Client engineer arrived Honny Power factory together with the Third Inspection Party (CCIC, Shanghai) auditor and tested three diesel generators for first shipment.


Honny Engineers performed all testing program according to the inspection schedule and specification, including visual checking, mechanical checking, electrical checking, operation testing, load testing, and protection testing. With the signature by Client, CCIC, Honny Power, Three units high voltage generator passed through the factory testing. Honny Power will arrange the shipment to client site in following days after package and custom applying.


The 26MW power station system is consist of two city supplying from 15MVA transformer, 33kV/6.3KV. Every 4 unit 3.2MW DG set consist one group and connected to one transformer. There is one couple VCB between two city supplying. Honny will provide all controls for generator synchronization and load sharing, couple VCB logic control, City supplying incoming VCB control.



QQ客服

QQ客服

在线客服

咨询电话